Mar 24, 2023

Work will begin on N-92 from Broadwater to US-385/N-92 junction

Posted Mar 24, 2023 10:15 AM

NDOT

GERING — Weather permitting, work will begin March 27 on N-92, from reference post 64+66 to reference post 75+45, according to the Nebraska Department of Transportation.

Werner Construction LLC of Hastings is the contractor for the project. Work includes bridge repair, minor grading, culverts and guardrail. The bridge repair will occur in two phases. Temporary traffic signals and a concrete barrier curb will be installed across the bridge during the repair.

Traffic on the North Platte River bridge will be reduced to one lane. Traffic will be maintained with lane restrictions, a pilot car and flaggers. A 10-foot width restriction will be in effect. Anticipated completion is September.