Jul 23, 2024

Work will begin on I-80, Sidney–Sunol and Sidney Westbound Rest Area

Posted Jul 23, 2024 10:00 PM

Nebraska Department of Transportation

 (Gering, Neb.) — Weather permitting, work will begin August 5 on eastbound and westbound I-80 and the westbound rest area at Sidney, from reference post 60.68 to reference post 68.67 according to the Nebraska Department of Transportation.

Paulsen, Inc. of Cozad is the contractor for this project. Work includes pavement repair, milling old asphalt and repaving with a new asphalt overlay, bridge girder repairs, and new guardrail and grading.

The westbound rest area will be removed. New ramps and parking lot will be built to accommodate a new rest area building being constructed under a separate project. Traffic will be maintained with lane closures. Anticipated completion is July 2025.

Motorists are reminded to drive cautiously in and near work zones, to buckle up, and to put phones down.